Construction of Tema Motorway Interchange Upgrade — Phase 2
Financial summary
Estimated value
₵48,000,000.00
At procurement stage
Awarded amount
₵47,200,000.00
Current contract value
₵51,800,000.00
+1 amendment
Total recorded payments
₵21,400,000.00
41% of contract value
Tender
Tender status
Opening date
Closing date
Eligibility requirements
Bids received
1 bid recorded.
This tender received only one recorded bid. This is a review signal — it does not indicate wrongdoing.
| Reference | Submitted | Bidder | Status | Amount |
|---|---|---|---|---|
| BID-2026-MOR-001A | 8 Mar 2026 | Accra BuilderCo Ltd | Awarded | ₵47,200,000.00 |
Award
Supplier
Amount
Award date
Status
Justification
Timeline
Procurement published
15 Jan 2026 · Ministry of Roads and Highways
Tema Motorway Interchange Upgrade published to OpenContract.
Simulated demo anchor on Base Sepolia. Demonstrates the cryptographic anchoring schema.
0x8a4f2e31...8e2f1a4bTender published
20 Jan 2026 · Ministry of Roads and Highways
Tender open until 10 March 2026.
Simulated demo anchor on Base Sepolia. Demonstrates the cryptographic anchoring schema.
0x4b7c9d1e...a5b7c9d2Award published
28 Mar 2026 · Ministry of Roads and Highways
Award published to Accra BuilderCo Ltd (GHS 47,200,000.00).
Simulated demo anchor on Base Sepolia. Demonstrates the cryptographic anchoring schema.
0xc2e4f6a8...2e4f6a8bContract signed
12 Apr 2026 · Ministry of Roads and Highways
Contract CTR-2026-MOR-0012 executed and signed.
Contract amended (Amendment #1)
20 Jun 2026 · Ministry of Roads and Highways
Variation approved: +GHS 4,600,000.00 for soil remediation.
Further stages to be recorded
Documents
Review signals
These signals highlight patterns that may warrant additional review. They are not findings of wrongdoing.
Single bidder
Only one bid was received for this open tendering process. While technically compliant, a single submission limits competitive validation of pricing and quality.
Significant amendment
Contract value increased by GHS 4,600,000 (9.75%) via Amendment #1, attributed to unforeseen ground conditions. The change exceeds the significant amendment threshold of 5%.
Export data
Data exported in Open Contracting Data Standard (OCDS) format.